Christmas Mountain Sanitary District, Town of Dellona, 2014

Lift Station No. 13 at Christmas Mountain Resort had three different types of submersible pumps in its septic tank’s effluent pump chamber. It was built in a drainage way and experienced flooding and debris deposition through its leaking tank risers. The decision was made to replace the station with a new above ground valve vault lift station, including a new 3-phase electric service. The finished project not only met the design requirements but also the aesthetic needs of the location.

Services Rendered: Municipal Engineering, Water and Wastewater Design

Christmas Mountain Sanitary District
Lift Station Replacement

  • Christmas Mountain Lift Station - Pre-Project